UK Power Networks have advised us they will be undertaking work on our main incoming power feed for our Horsham Data Center between 14:00 and 18:00 on Friday the 21st June. We will be running on backup power for the duration of the works.
Both UKPN and Structured engineers will be on site for the duration. No impact is expected but the site will be classed as “at risk”
Load tests will be completed prior to the works to ensure a smooth transfer.
UPDATE 01 – 14:29
The site is now on backup power.
UPDATE 02 – 16:00
This work is now complete and the facility is now back on grid power with both A and B feeds being back in service. No service disruption was experienced.